Client
Grifols
Value
€2,800,000
Programme Duration
1 Year
Completion Date
November 2015
Location
Grangecastle, Dublin 22
Project Managers
Stewards
Design Team
PM Group
Quantity Surveyors
Stewards
Project Type
New Build Distribution Centre
Scope
Design, supply & install; Fire rated steel doors, Fire rated Coldroom & Freezer room doors, Rapid action doors, Automated sliding doors, Interlocking and access control, Cleanroom Doors
Design Package
Auto CAD
This project for Grifols Worldwide Operation Ltd involved the development of a fully serviced international logistics centre with automated storage, cleanrooms, laboratories, coldrooms in Grange Castle, Co Dublin.