Project Details

Client

Pfizer

Value

Not Disclosed

Programme Duration

3 months

Completion Date

February 2014

Location

Grangecastle, Dublin

Project Managers

Sisk

Design Team

PM Group

Quantity Surveyors

Sisk

Project Type

Biopharma Facility Refurbishment

Scope

Design, supply, install & commission temperature controlled cleanrooms

Design Package

BIM, Revit & CFD Modelling

Pfizer is one of Ireland’s leading employers and the largest pharmaceutical sector investor and employer. Grange Castle was established in 2006 and is part of a world-leading protein drug  discovery unit within Pfizer Worldwide R&D. In 2014 Pfizer Grangecastle underwent a considerable refurbishment bringing their production facility up to current biopharma requirements. As an integral part of the project Modubuild supplied a turnkey low temperature cleanroom for the storage of biopharma product and temperature regulation of materials during the production of biologics.

“Quote Needed”

– Client Representative

Lorem Ipsum is simply dummy text of the printing and typesetting industry. Lorem Ipsum has been the industry’s standard dummy text ever since the 1500s.

Like What We Do?